Periodic inspection of work equipment in Turkey: intervals and equipment list
What periodic inspection of work equipment means under Turkish regulations, which equipment is covered and the maximum intervals, with a table.
Under the Turkish Regulation on Health and Safety Conditions in the Use of Work Equipment, periodic inspection is the examination and/or testing of work equipment by authorised persons at the intervals and by the methods the regulation sets. The covered equipment and the maximum intervals are listed in the tables of Annex III. Where the standards give no period, the maximum is one year for most equipment and six months for building scaffolds.
Your occupational health and safety (OHS) specialist says, “Let’s gather the inspection reports for the compressor, the forklifts and the earthing system.” The equipment is with different people, the reports are in different folders, and nobody can tell at a glance when each inspection falls due. The problem is not only paperwork: a pressure vessel or a lifting appliance that has not been inspected on time is a risk for the people who work with it. This article summarises, from the official text, which equipment is subject to periodic inspection under Turkish law and where the inspection intervals come from.
Periodic inspection of work equipment is the examination and/or testing of work equipment by authorised persons at the intervals and by the methods set out in the regulation. The legal basis is the Turkish Regulation on Health and Safety Conditions in the Use of Work Equipment; we read the provisions below from the current text on mevzuat.gov.tr (reviewed on 23 October 2026). At the end, we also explain what the Reminder Module of YazSis KurumsalPortal does on the tracking side.
What is periodic inspection, and which workplaces and equipment does it cover?
The regulation covers all workplaces within the scope of Law No. 6331 on Occupational Health and Safety (Art. 2). Work equipment means all machines, tools, devices, apparatus, plants and installations used to carry out work (Art. 4). However, not every piece of work equipment is subject to periodic inspection under the regulation: according to Art. 7, the equipment or equipment groups listed in the tables of Annex III are subject to inspection, and these inspections are carried out by persons authorised to perform periodic inspections.
Maintenance and periodic inspection are separate concepts. The regulation defines maintenance as overhaul, repair, replacement, adjustment, troubleshooting, cleaning and calibration; the person who maintains a piece of equipment may not carry out the periodic inspection of the equipment they maintain (Art. 14/A).
Work equipment periodic inspection list: which groups are covered?
Annex III lists the equipment groups in six tables. Each group typically includes the following:
- Pressure vessels and installations (Table 1): steam and hot water boilers, heating boilers, compressed air tanks, autoclaves, LPG tanks.
- Lifting and conveying equipment (Table 2): cranes, hoists, industrial trucks such as forklifts and pallet trucks, lifting platforms, building scaffolds, conveyors, lifting accessories such as slings and clamps.
- Installations (Table 3): electrical and earthing installations, lightning protection, generators, transformers, fire extinguishing systems, portable fire extinguishers, fire detection, ventilation and air conditioning.
- Machine tools (Table 4): presses, lathes and milling machines, drilling machines, guillotine shears.
- Industrial racks and doors (Table 5).
- Construction machinery (Table 6): loaders, excavators, dump trucks, concrete pumps.
The periodic inspection of lifts, on the other hand, is subject to the Turkish Regulation on Periodic Inspection of Lifts, according to item 2.2.4 of Annex III. The standards named in the tables are given as examples; standards not listed in the tables or published later are also taken into account (Annex III, 1.11).
What are the periodic inspection intervals for work equipment?
The rule works in this order: the inspection interval is first set according to the relevant standards and, failing that, according to the values set by the manufacturer; if neither exists, a risk assessment based on factors such as workplace conditions and the frequency and duration of use is used. If the standards do not specify a period, the inspection frequency may not exceed the maximum periods in the tables (Annex III, 1.4). The table below summarises selected examples from Annex III:
| Equipment group | Examples | Maximum period (if the standard gives none) |
|---|---|---|
| Pressure vessels and installations | Steam boiler, heating boiler, compressed air tank | 1 year |
| LPG and similar liquefied gas tanks | Underground and above-ground tanks | Within the period given in the written plan (examination only); reassessment at the end of 10 years |
| Lifting and conveying | Cranes, industrial trucks such as forklifts and pallet trucks, lifting accessories | 1 year |
| Lifting and conveying | Building scaffolds | 6 months |
| Installations | Electrical and earthing installations, lightning protection installation, generator | 1 year |
| Installations | Fire extinguishing systems, portable fire extinguishers, fire detection and alarm systems | 1 year |
| Machine tools | Presses, lathes and milling machines, guillotine shears | 1 year |
| Industrial racks and doors | Industrial racks, industrial doors | 1 year |
| Construction machinery | Loader, excavator, concrete pump | 1 year |
| Lifts | Lifts within the scope of the Lift Regulation | According to the Regulation on Periodic Inspection of Lifts |
The table is a summary; rows such as atmospheric storage tanks and cryogenic tanks contain different periods. Always look up the row for your own equipment in the official text.
When and by whom is the periodic inspection carried out?
- Equipment whose safety depends on installation and assembly conditions is inspected after installation and before first use; inspections are also carried out after major maintenance and repairs and each time non-mobile equipment is moved to a new location (Art. 7).
- For equipment exposed to effects that can cause faults, the necessary inspections are carried out after events such as changes in the way of working, accidents, natural events or long periods of non-use (Art. 7).
- The inspection is carried out by authorised persons registered in EKIPNET who are engineers, technical teachers, technicians or senior technicians from the relevant disciplines; the report must show the authorised person’s EKIPNET registration number (Art. 4 and 7).
- The employer and the authorised person sign a contract in line with the template in ISG-KATIP no later than one day before the inspection service (Art. 7).
- For some equipment, such as tower cranes, LPG tanks and installations, escalators and suspended access equipment, the inspection may only be carried out by authorised persons working at equipment inspection bodies (Additional Art. 2); for the four items added to this list in December 2025, the requirement has been postponed to 1 January 2027.
From inventory to inspection calendar: five steps
- Take an inventory: List the machines, installations, tanks, lifting appliances and similar equipment at the workplace with code, brand, model and location.
- Match it with Annex III: Mark which table and which row each piece of equipment falls under; note separately the items with no match in the tables.
- Set the interval: Write down the interval given by the standard, the manufacturer or the table; for unclear cases, ask your occupational health and safety specialist for a risk assessment.
- Enter the last inspection date: From the reports you have, take each item’s last inspection date and the next inspection start date stated in the report.
- Set up the calendar: Collect the dates in one place, assign a responsible person and close each completed inspection with a record.
Once these five steps are done, the question “Is this inspection due?” no longer depends on one person’s memory; it becomes a matter of looking at a list. In the first round, the inventory usually takes the longest, because there is rarely one person who knows all the equipment at the workplace.
Tracking inspections with a spreadsheet and folders: whose memory does it depend on?
If you have only a few items, a spreadsheet with the equipment name, the last inspection and the next inspection date is enough as a first step. The breaking points are familiar: the spreadsheet does not send alerts, tracking stops when the person who enters the next date leaves, the report from the inspection company stays in an e-mail, and the dates are spread across different people by equipment type. The message “the compressor report has arrived” in a WhatsApp group is information that nobody can find a few weeks later. The problem here is less the tool than the fact that date tracking depends on one person’s attention.
Tracking inspection dates in the portal
The Reminder Module tracks inspection, permit, contract, maintenance and periodic check dates with recurrence rules. Work equipment inspection dates are among them. The flow has five steps: create the record, set the date, choose the recurrence rule, notify automatically, record completion. Alerts are sent 30, 7 and 1 day before the critical date by portal notification, e-mail and SMS; e-mails go out through the organisation’s own SMTP account and SMS through its own NetGSM account. The completion of each period is recorded, and the inspection history can be followed in one place.
The portal only helps with tracking dates and records; it does not decide which equipment is subject to inspection, what its interval is or whether a report is adequate. These decisions belong to the regulation, the authorised person and your occupational health and safety specialist. If you also want to track the fault and maintenance history of the equipment, the Maintenance & Fault Management module keeps it together with the equipment history. If you want to track the deficiencies stated in the inspection report as findings, the Internal Audit Management module turns each finding into a corrective action with a clear owner, deadline and evidence.
Frequently asked questions
What is periodic inspection?
It is the examination and/or testing of work equipment by authorised persons at the intervals and by the methods set out in the Turkish regulation. The result is documented in a periodic inspection report.
Where can I find the list of work equipment subject to periodic inspection in Turkey?
The equipment and equipment groups subject to inspection are listed in the Annex III tables of the Turkish Regulation on Health and Safety Conditions in the Use of Work Equipment. The ministry also publishes equipment-specific inspection report and criteria documents; the table in this article is only a summary.
How is the inspection frequency set if neither the table nor the standard gives a period?
First, the interval set by the manufacturer is checked. If there is none, a risk assessment is carried out based on factors such as workplace conditions and frequency of use. If the standards do not specify a period, the maximum periods in the table may not be exceeded.
Who carries out the periodic inspection?
Authorised persons registered in EKIPNET who are engineers, technical teachers, technicians or senior technicians from the relevant disciplines. For some equipment, the inspection may only be carried out by authorised persons working at equipment inspection bodies. The person who maintains a piece of equipment may not carry out its periodic inspection.
Does the Reminder Module track periodic inspection dates?
Yes. The Reminder Module of YazSis KurumsalPortal tracks work equipment inspection dates with a recurrence rule, sends alerts 30, 7 and 1 day before the date and records completed periods. It does not judge whether equipment meets the requirements.
Sources
- Turkish Regulation on Health and Safety Conditions in the Use of Work Equipment (mevzuat.gov.tr)
- Turkish Official Gazette, 23 December 2025, No. 33116: amendment to the regulation
- Turkish Ministry of Labour and Social Security, OHS Directorate General: announcement of 24 December 2025
Last legal review: October 23, 2026
More articles
What is employee onboarding? Process stages, owners and checklist
What is onboarding? It is more than a first-day welcome. It is a process in which paperwork, account, asset assignment, training and orientation steps are shared across departments; this article separates the stages and the owners.
November 21, 2026 · 8 min readMobile app or web app? Choosing between native, mobile web and PWA for staff
Make employees download an app, or let them use the phone browser? We compare native apps, mobile-friendly web and PWAs on installation, notifications, camera and maintenance effort.
November 21, 2026 · 8 min readHow to choose an e-commerce infrastructure? Ready-made, open source or custom
Three quotes, three different paths: a ready-made rental package, an open source installation and custom development. We use questions on flexibility, integration and ownership to work out which one fits you.
November 21, 2026 · 8 min read