How is an ERP migration done? Data migration, parallel run and go-live steps

How is an ERP migration done? Scope, data cleaning, mapping, trial transfer, parallel run and go-live steps, plus moving data from Excel and an old program.

FUFerhat UğurluYazSis TeamPublished: November 5, 20268 min read
In short

The answer to how an ERP migration is done is stages: limit the scope, clean the old data, map the fields to the new system, run a trial transfer and compare the figures with the old records, run in parallel for a set period, and go live once the checks hold. The method for moving data from Excel and an old program is set per project; this article offers no ready-made migration tool or timeline promise.

Friday evening. Which program will the person entering new orders on Monday morning open? Which system will the warehouse count be posted to? Are the open orders in the old program in the new system? These questions are usually asked right before the switch, in the last meeting, and nobody has the answers. The hard part of an ERP migration is not installing the software but answering these questions beforehand; go-live day is the most expensive time to look for answers. An ERP migration is the process by which a business moves its sales, purchasing, stock, production and finance processes from old tools (Excel, an old program, paper) to a new ERP system, carrying the data and the working habits along with it.

If the stages below are followed in order, the migration is not squeezed into a single risky weekend. Let us say up front that durations vary by project; this article promises no calendar, it explains how you will know what is finished at each stage.

ERP migration stages and the exit criterion for each stage

StageWhat is doneHow you know it is done
1. ScopeDecide which processes and modules to start with and which come laterThe written first-phase list has been approved by those concerned
2. Data cleaningDuplicate, missing and wrong records in the old data are weeded outRules for codes, units and names are set; data owners have done the cleaning
3. MappingOld fields are matched to the fields in the new systemSource, target and transformation rule are written for each field
4. Trial transferData is moved to a test environment and the figures are compared with the old recordsStock quantity, number of accounts and balances match the old records
5. Training and permissionsUsers try their own transactions with test data; permissions are definedEach role can do its own work from start to finish
6. Parallel runFor a set period, results are compared with the old methodThe difference list is closed and the agreed criterion is met
7. Go-liveThe old system becomes read-only and the new system becomes the single place of recordOpening data matches; rollback conditions are written

How do we move stock and account data from the old program to the new ERP?

Before moving data, also decide what you will leave behind in the old program. If inactive stock cards accumulated over the years, accounts that will never be worked with again and closed orders are moved to the new system, lists get crowded, search slows down and users pick the wrong card. Historical records can remain read-only in the old system; only data that will be useful from today on goes into the new system.

First decide what will be moved, then how. Each type of data carries a different risk; the table below summarizes the most commonly moved data and how to check each.

DataWatch out when movingHow to check
Stock cardsMake codes unique; write units and descriptions consistently; do not move unused cardsThe active card list is compared with the old records
Stock quantityTake a count before moving; enter opening quantities by warehouse and locationThe total by warehouse should match the count list
Account cards (customers and suppliers)Duplicate names are merged; contact and tax details are updatedThe number of accounts and the active/inactive split are compared
Account balancesOpening balances are settled together with the outside accountant’s recordsThe balance total matches the accounting record
Open ordersUndelivered items are entered in the new system as open ordersThe remaining quantity on each order is checked by hand
Bill of materials and recipeOnly the current version is moved; old versions stay in the archiveMaterial requirements for a few products are calculated by hand and compared

The rule is simple: wherever you move numbers, put the totals before and after the move side by side. If quantity, balance or record count does not match, do not count the transfer as finished.

Importing Excel data into an ERP: automation or by hand?

For a one-time import from Excel, a properly prepared template is often enough: fixed column headers, a unique code on each row, units and categories spelled one way. If the volume is small, the import can be done from the import screen; if the volume is large, the codes are inconsistent or data from several files will be merged, writing an import script may be necessary. The method is set per project; we do not promise a ready-made migration tool or a timeline. A file that flows into the ERP regularly (for example, importing a daily Excel output every morning) is a separate matter from a one-time move: it is an integration matter.

How are the parallel run and go-live managed?

A parallel run means carrying out the same transactions in the new system for a set period and comparing the results with the old method. It takes extra effort; in return it gives confidence in critical calculations such as month-end close and stock and account balances. It is not needed in every business, but it should be considered for processes where the cost of error is high. On go-live day the order is:

  1. The final data cut is taken, and from that moment no new records are entered into the old system.
  2. Opening balances, stock and open orders are loaded into the new system.
  3. The control totals are compared with the old records; if there is a difference, the system does not go live.
  4. The old system is made read-only; it stays in the archive for retrospective queries.
  5. On the first day, a support person stands by for each role.
  6. Rollback conditions are written down from the start: in which case, who decides, and how to go back.

How do you prepare users for the migration?

Even if the technical part of the migration is done right, the system stays empty if users go back to old habits. Plan these four things for preparation:

  • Role-based trial: Let the warehouse worker, the buyer and the sales rep each do their own real work from start to finish in the test environment.
  • Closing the old habit: After go-live, state clearly that the old Excel files will no longer be updated and that the new system is the place of record.
  • A support point for the first period: Name a single person or channel where questions are collected; it keeps the same question from coming in from ten people.
  • A feedback loop: List the gaps and adaptation requests that appear in the first period, and put them in priority order.

Go-live is not an end but the first measuring point. Verifying once more at the end of the first period that the stock count, open orders and account balances match the system is the cheapest way to catch the remaining errors while they are small.

Managing the migration with Excel: where does it work, where is it not enough?

Keeping the migration plan, the field-mapping table and the difference list in Excel works perfectly well; everyone knows the tool and it needs no extra setup. The places where it struggles are clear:

  • Versions of the mapping table multiply, and which one is current gets confused.
  • Data owners clean their own files separately, and merging them becomes a job of its own.
  • As the difference list grows, it cannot be tracked who closed what.
  • If the trial transfer is done by hand every time it is repeated, human error gets into the transfer itself.

How do YazSis ERP and the integration side handle migration?

One of the principles on the YazSis ERP page is keeping the existing system: missing processes are completed without ripping out a working ERP, and data is joined through API and database integrations. So not every migration has to take the form “close the old completely, open the new”; for some businesses a gradual path carries less risk. The scope is set by needs analysis in each project.

The Integration page describes joining ERP and accounting, payroll and time-and-attendance (PDKS), CRM and e-commerce, bank, production and warehouse, and SMS and e-mail systems in a controlled data flow. Four principles also fit a migration plan: identifying a single reliable source for each data field, designing the direction, frequency and error scenarios of the flow, setting up logs, permissions, retries and data validation, and making the health of the integration visible. If both systems keep records for the same field during the migration period, the question “which one is right?” comes up; that is why the single-source principle is also the first item of the migration plan.

If you want to assess your ERP migration scope and data-migration need together, you can request a meeting from the ERP and Integration pages.

Frequently asked questions

How does the ERP implementation process work?

The process usually goes through scope definition, data cleaning, field mapping, trial transfer, training and permissions, parallel run and go-live. Every stage should have an exit criterion; you do not move on to the next stage until the criterion is met.

Is it possible to automate importing Excel data into an ERP?

For a one-time import, an orderly template is often enough. For data that is large in volume, inconsistent or coming from several files, an import script may be needed, and for a regular flow, an integration. At YazSis the method is set per project; there is no ready-made migration tool or timeline promise.

Is a parallel run mandatory?

It is not mandatory for every business. For accounts where the cost of error is high, such as month-end close and stock and account balances, comparing the results with the old method gives confidence before go-live.

Should the old program be shut down after go-live?

Usually the old system is not deleted but made read-only. That way new records are kept in one place, while retrospective queries and checks can still be made from the old system.

Which step of an ERP migration is the riskiest?

Most often it is data cleaning and mapping. If wrong or duplicate records are moved to the new system as they are, the problems show up in live use. Comparing the totals with the old records in the trial transfer reveals this risk early.